KavanahKavanah

AI Agents

Auto-Planning

AI builds your sprint

Smart Triage

Auto-prioritize & assign

Agent Workflows

Automate any process

Risk Detection

Flag blockers early

Platform

Boards & Views

Kanban, timeline, list

Team Spaces

Shared project hubs

Team Chat

Communicate in context

Smart Alerts

AI-curated notifications

Learn

Courses

Two free courses

Blog

Tips and updates

Documentation

Guides and references

Support

Help Center

Get answers fast

Community

Connect with others

Trust & Compliance

SOC 2, ISO, HIPAA, GDPR

PricingApps
Log inGet started
GUIDE

Sprint Estimation With p50 and p90: Why Your Commitment Should Be the 90th Percentile

+
+

Oct 24, 2026

Will Schulz

Written by:

Will Schulz

Sprint Estimation With p50 and p90: Why Your Commitment Should Be the 90th Percentile
Listen
0:00 / ~2:55

Sprint estimation goes wrong in the same direction almost every time: work takes longer than planned. The usual response is to ask people to estimate better, which does not work, because the estimate is not the problem. The problem is that a single number hides its own uncertainty. Planning with p50 and p90 makes that uncertainty explicit. The p50 is the median outcome, the one you hit half the time. The p90 is the one you hit nine times in ten. A team that commits at p50 is flipping a coin every sprint.

1. Where the Two Numbers Come From

Kavanah takes each person's completed tasks from the last 90 days that have both an estimate and logged hours, and computes the ratio of actual to estimate for each. The median of those ratios is that person's p50 multiplier; the 90th percentile is their p90 multiplier. A developer who usually takes 1.2 times their estimate, and sometimes 1.8 times, gets those two numbers. Someone with fewer than five completed samples inherits the team's distribution until they have enough history of their own.

2. Why the Stored Estimate Is Never Changed

It is tempting to write the uplifted number back onto the task. Do not. Calibration divides actual hours by the stored estimate, so if you store the uplifted value, the next ratio measures an already-corrected number, drifts toward 1.0, and the correction quietly unwinds itself. Kavanah applies the uplift only in the planner's forecast and leaves the estimate as the person wrote it.

3. Floors That Keep the Forecast Safe

A team that consistently over-estimates would produce a multiplier below one, which would shrink commitments below the estimates themselves. That is the opposite of what the mechanism exists for, so the p50 multiplier is floored at 1 and the p90 is never allowed below the p50. The forecast can only add caution, never remove it.

4. How to Use the Two Lists

The planner packs the unstarted backlog into the team's capacity twice and reports what fits at each level, per person, with the deferred work listed. Commit the p90 list. Put the difference between the two lists on the board as stretch. When the sprint goes well, the stretch work gets done and nobody is surprised; when it goes badly, the commitment still holds.

5. What This Fixes Downstream

DORA's 2024 research linked unstable priorities to lower productivity and higher burnout. Sprints that spill over are a quiet source of instability: every miss re-cuts the next sprint and moves the roadmap. Committing at p90 makes the sprint a promise the team keeps, which makes the quarter predictable, which is what everyone above the team actually wanted from the estimates in the first place.

Ask the agent for a sprint recommendation and Kavanah returns both lists; committing one is a person's decision in the Sprint Planner. For the rest of the planning, code and AI requirements a tech company should check, see our project management software for tech companies page.

Part of the guide

Project management software for tech companies

Sources

  1. 01Accelerate State of DevOps Report 2024 — DORA
  2. 02Project Management Software for Tech Companies: Sprints on Real Numbers, Code-Linked Tasks and AI Agents You Can Audit — Kavanah

You might want to read

More Blog
+
+
IT Project Management Software: Eight Things to Require Before You Buy
GUIDE

IT Project Management Software: Eight Things to Require Before You Buy

IT teams buy a project tool and then spend a year working around it. Here are the eight requirements that decide whether it fits: code links, honest estimates, agents with limits, an API, and the security answers your own customers will ask for.

SaaS Roadmap to Release: Turning Quarterly Bets Into Sprints That Actually Ship
GUIDE

SaaS Roadmap to Release: Turning Quarterly Bets Into Sprints That Actually Ship

A SaaS roadmap is a list of bets. A sprint is a promise. Most teams lose the thread between the two. Here is how to keep the year, the quarter and the sprint connected without re-planning every fortnight.

GitHub Issues and Project Tasks: How a Two-Way Sync Avoids the Infinite Loop
GUIDE

GitHub Issues and Project Tasks: How a Two-Way Sync Avoids the Infinite Loop

Two-way sync sounds simple until the first edit bounces back and forth forever. Here is how to keep GitHub Issues and your project tasks in step, which fields to sync, and which to leave alone.

KavanahKavanah

© AW3 Technology, Inc. All rights reserved.