Summary
- Project:
- Week ending:
- Overall status (Green / Amber / Red):
- One-sentence summary:
Workstream status
Green: on track. Amber: at risk, recovery plan in place. Red: off track, needs a decision or help.
| Workstream | Status | Done this week | Next week | Owner |
|---|---|---|---|---|
| Design | Green | Final screens approved | Hand designs to engineering | Designer |
| Engineering | Amber | Sign-up flow built; password reset half done | Finish password reset; start onboarding | Engineering lead |
| Content | Green | Help articles drafted | Review drafts with support | Content lead |
| Launch | Red | Launch date proposed | Decision needed on date (see below) | Project lead |
Completed this week
- Deliverable or task finished — owner
- Deliverable or task finished — owner
Planned for next week
- Task — owner — due date
- Task — owner — due date
Risks and blockers
Say what you are doing about each one and what you need from the reader.
- Risk or blocker — impact — what we are doing — help needed
Decisions needed
- Decision — options — recommendation — needed by (date)
Key dates
- Next milestone and date:
- Deadline, and whether it is still achievable: