Risk register
Score = likelihood × impact, each rated 1 (low) to 5 (high). Review the highest scores first.
| ID | Risk | Category | Likelihood (1-5) | Impact (1-5) | Score | Owner | Response | Trigger | Status |
|---|---|---|---|---|---|---|---|---|---|
| R1 | A key vendor delivers late | Schedule | 3 | 4 | 12 | Project lead | Mitigate: agree interim dates and check weekly | Missed interim date | Open |
| R2 | A specialist is pulled onto another project | People | 2 | 5 | 10 | Sponsor | Mitigate: document their work; line up a backup | Resourcing request from another team | Open |
| R3 | Requirements change after design sign-off | Scope | 4 | 3 | 12 | Project lead | Mitigate: change requests go through the sponsor | New request from a stakeholder | Open |
| R4 | Costs exceed the approved budget | Budget | 2 | 4 | 8 | Finance contact | Monitor: compare spend with budget every two weeks | Spend above plan for two periods | Open |
| R5 | Data migration finds poor-quality records | Technical | 3 | 3 | 9 | Engineer | Mitigate: run a trial migration early | Trial error rate above agreed level | Open |
| R6 | Launch clashes with a busy period for users | External | 2 | 2 | 4 | Project lead | Accept: note it and review at go/no-go | Open |
Scoring guide
- Likelihood 1: very unlikely. 3: about as likely as not. 5: almost certain.
- Impact 1: negligible. 3: noticeable delay, cost or quality loss. 5: threatens the project's objective.
- Score 15 to 25: act now and report to the sponsor. 8 to 14: plan a response and watch the trigger. 1 to 7: monitor.
Response types
- Avoid: change the plan so the risk cannot happen.
- Mitigate: reduce the likelihood or the impact.
- Transfer: move the impact to someone better placed to carry it, such as a vendor or insurer.
- Accept: decide consciously to live with it, and say so in the register.
Review
- Review frequency:
- Who attends:
- Where closed and realized risks are recorded: