Change request form
- Change request ID:
- Project:
- Requested by and date:
- Description of the change:
- Reason for the change:
- What happens if we do not make it:
Impact assessment
Filled in by the project lead before the decision. Say "none" rather than leaving a line blank.
- Scope: what is added, removed or altered:
- Schedule: effect on milestones and the end date:
- Cost: extra effort, spend or fee:
- Quality and risk: what could go wrong as a result:
- Other projects or teams affected:
- Options considered (including doing nothing):
- Recommendation:
Decision
- Decision (Approved / Rejected / Deferred):
- Decided by:
- Date:
- Conditions or notes:
Change log
One row per request, kept for the whole project, including rejected ones.
| CR ID | Date raised | Requested by | Change | Schedule impact | Cost impact | Decision | Decided by | Date decided | Status |
|---|---|---|---|---|---|---|---|---|---|
| CR-01 | 2026-11-03 | Client sponsor | Add a second language to the help centre | 2 weeks | 8 days of effort | Approved | Sponsor | 2026-11-06 | In progress |
| CR-02 | 2026-11-10 | Marketing lead | Move launch forward by one week | Minus 1 week; testing compressed | None | Rejected | Sponsor | 2026-11-12 | Closed |
| CR-03 | 2026-11-17 | Engineering lead | Replace the reporting library with a supported one | 3 days | None (within contingency) | Approved | Project lead | 2026-11-18 | Done |
| CR-04 | 2026-11-21 | Client operations | Export data to the client's finance system | To be assessed | To be assessed | Pending | Assessing |
Decision rights
- Changes within contingency and with no effect on the end date: project lead.
- Changes that move a milestone or use more than the contingency: sponsor.
- Changes that alter the contract, fee or a client deliverable: sponsor and the client.