Project details
- Project:
- RAID log owner:
- Review frequency:
- Last reviewed:
RAID log
One row per item. Type is Risk, Assumption, Issue or Dependency. Severity is High, Medium or Low.
| ID | Type | Description | Impact if it goes wrong | Severity | Owner | Action | Review date | Status |
|---|---|---|---|---|---|---|---|---|
| R1 | Risk | The vendor's API changes before our integration is finished | Rework and a slipped test phase | Medium | Engineering lead | Pin the API version; ask the vendor for their change schedule | 2026-12-04 | Open |
| A1 | Assumption | The client's data team can supply test data by week 3 | Testing cannot start on time | High | Project lead | Confirm the date in writing with the client's data lead | 2026-11-27 | Open |
| A2 | Assumption | Current hosting can handle launch traffic | Slow or failed launch | Medium | Engineer | Run a load test before the go/no-go meeting | 2026-12-11 | Open |
| I1 | Issue | Design sign-off is a week late | Build start has slipped | High | Sponsor | Hold a decision meeting with the approvers this week | 2026-11-26 | Open |
| D1 | Dependency | Security review from the central IT team | Cannot go live without it | High | Project lead | Book the review slot now; send the documents a week ahead | 2026-12-01 | Open |
| D2 | Dependency | Marketing copy for the launch page | Launch page ships with placeholder text | Low | Marketing contact | Agree a draft date at the next sync | 2026-12-08 | Open |
What each type means
- Risk: an uncertain event that would affect the project if it happened. Record it before it happens.
- Assumption: something the plan treats as true without proof. Record who will confirm it, and by when.
- Issue: a problem that is happening now and needs action. It does not need a likelihood; it already happened.
- Dependency: something the project needs from outside the team, such as a deliverable, a decision or access.
Moving items between types
- An assumption that proves false becomes an issue if it is already hurting the plan, or a risk if it might.
- A risk that happens becomes an issue; close the risk and link the new issue to it.
- A dependency that misses its date becomes an issue.
Review
- Who attends the review:
- Items escalated to the sponsor this period:
- Items closed this period: